Fire Penetration Resistance of Thermal/Acoustic Insulation Installed on Transport Category Airplanes
other · Rule · Final rule. · Published 2007-01-12 · Effective 2007-02-12 · 72 FR 1438
Document
Document number
E7-338
Federal Register citation
72 FR 1438
Type
Rule
Action
Final rule.
Category
other
Publication date
2007-01-12
Effective date
2007-02-12
FAA docket
Docket No. FAA-2006-24277
Abstract
The FAA extends, by 24 months, the date for operators to comply with the fire penetration resistance requirements of thermal/ acoustic insulation used in transport category airplanes manufactured after September 2, 2007. This extension is from September 2, 2007, to September 2, 2009. This action is necessary to allow airframe manufacturers enough time, after getting an acceptable certification test facility, to select and certificate appropriate installations.