Federal Acquisition Regulation; Independent Government Estimates- Construction
other · US Department of Defense · Rule · Published 1997-08-22 · Effective 1997-10-21 · 62 FR 44829
Document
Document number
97-21501
Federal Register citation
62 FR 44829
CFR reference
48 CFR 36
Type
Rule
Action
Final rule.
Category
other
Sub-agency
US Department of Defense
Publication date
1997-08-22
Effective date
1997-10-21
DOD docket
FAC 97-01
Abstract
The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council have agreed on a final rule amending the Federal Acquisition Regulation (FAR) to increase the threshold for a mandatory independent Government estimate of construction costs and architect-engineer costs from $25,000 to $100,000. This regulatory action was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993, and is not a major rule under 5 U.S.C. 804.