Standardization of Small Generator Interconnection Agreements and Procedures
electric-grid · Federal Energy Regulatory Commission · Published 2005-06-13 · Effective 2005-08-12 · 70 FR 34190
Document
Document number
05-11307
Federal Register citation
70 FR 34190
CFR reference
18 CFR 35
Type
Rule
Action
Final rule.
Category
electric-grid
Sub-agency
Federal Energy Regulatory Commission
Publication date
2005-06-13
Effective date
2005-08-12
Energy docket
Docket No. RM02-12-000
Abstract
The Federal Energy Regulatory Commission (Commission) is amending its regulations under the Federal Power Act to require public utilities that own, control, or operate facilities for transmitting electric energy in interstate commerce to amend their open access transmission tariffs to include standard generator interconnection procedures and an agreement that the Commission is adopting in this order and to provide interconnection service to devices used for the production of electricity having a capacity of no more than 20 megawatts. A non-public utility that seeks voluntary compliance with the reciprocity condition of an open access transmission tariff may satisfy this condition by adopting these procedures and agreement.