# Interconnection for Wind Energy
> **Federal Energy Regulatory Commission** · Final rule. · Published 2005-06-16 · Effective 2005-08-15 · 70 FR 34993
## Document
- **Document number:** 05-11678
- **Category:** electric-grid
- **Sub-agency:** Federal Energy Regulatory Commission
- **Federal Register citation:** 70 FR 34993
- **CFR reference:** 18 CFR 35
- **Publication date:** 2005-06-16
- **Effective date:** 2005-08-15
- **Energy docket:** Docket No. RM05-4-000-Order No. 661
## Abstract

The Federal Energy Regulatory Commission (Commission) is amending its regulations to require public utilities to append to their standard large generator interconnection procedures and large generator interconnection agreements in their open access transmission tariffs (OATTs) standard procedures and technical requirements for the interconnection of large wind generation.

## Source
- [Federal Register document](https://www.federalregister.gov/documents/2005/06/16/05-11678/interconnection-for-wind-energy)
---
*AI Analytics · CC0 1.0*