electric-grid · Federal Energy Regulatory Commission · Published 2005-12-19 · 70 FR 75005
Document
Document number
05-24173
Federal Register citation
70 FR 75005
CFR reference
18 CFR 35
Type
Rule
Action
Order on rehearing and clarification.
Category
electric-grid
Sub-agency
Federal Energy Regulatory Commission
Publication date
2005-12-19
Energy docket
Docket No. RM05-4-001
Abstract
The Federal Energy Regulatory Commission is granting in part and denying in part the requests for rehearing and clarification of its Final Rule on Interconnection for Wind Energy, Order No. 661. Order No. 661 requires public utilities that own, control, or operate facilities for transmitting electric energy in interstate commerce to append to their standard large generator interconnection procedures and large generator interconnection agreements in their open access transmission tariffs standard procedures and technical requirements for the interconnection of large wind generation.