Mandatory Reliability Standards for Interconnection Reliability Operating Limits; System Restoration Reliability Standards
electric-grid · Federal Energy Regulatory Commission · Published 2011-07-19 · 76 FR 42534
Document
Document number
2011-18066
Federal Register citation
76 FR 42534
CFR reference
18 CFR 40
Type
Rule
Action
Order on Clarification.
Category
electric-grid
Sub-agency
Federal Energy Regulatory Commission
Publication date
2011-07-19
Energy docket
Docket Nos. RM10-15-001 and RM10-16-001
Abstract
On March 17, 2011, the Commission issued Order Nos. 748 and 749, which approved new and revised Reliability Standards, including IRO-004-2 and EOP-001. In this order, we grant the North American Electric Reliability Corporation's (NERC) request for clarification of certain aspects of Order No. 748 including: The proper effective date language for Reliability Standard IRO-004-2; the correct version identification for the approval of EOP-001 intended by the Commission; and the proper effective date for Reliability Standard EOP-001-2. The Commission also grants NERC's request for clarification of Order No. 749 with respect to the version EOP-001 the Commission intended to approve and its effective date.