Mandatory Reliability Standards for Interconnection Reliability Operating Limits
electric-grid · Federal Energy Regulatory Commission · Published 2011-03-23 · Effective 2011-05-23 · 76 FR 16240
Document
Document number
2011-6778
Federal Register citation
76 FR 16240
CFR reference
18 CFR 40
Type
Rule
Action
Final rule.
Category
electric-grid
Sub-agency
Federal Energy Regulatory Commission
Publication date
2011-03-23
Effective date
2011-05-23
Energy docket
Docket No. RM10-15-000
Abstract
Under section 215 of the Federal Power Act, the Federal Energy Regulatory Commission (Commission) approves three new Interconnection Reliability Operations and Coordination Reliability Standards and seven revised Reliability Standards related to Emergency Preparedness and Operations, Interconnection Reliability Operations and Coordination, and Transmission Operations. These Reliability Standards were submitted to the Commission for approval by the North American Electric Reliability Corporation (NERC), which the Commission has certified as the Electric Reliability Organization responsible for developing and enforcing mandatory Reliability Standards. The Reliability Standards were designed to prevent instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the interconnection by ensuring that the reliability coordinator has the data necessary to assess its reliability coordinator area during the operations horizon and that it takes prompt action to prevent or mitigate instances of exceeding Interconnection Reliability. Operating Limits. The Commission also approves the addition of two new terms to the NERC Glossary of Terms. In addition, the Commission approves NERC's proposed revisions to Reliability Standards EOP-001-1, IRO-002-2, IRO-004-2, IRO-005-3, TOP- 003-1, TOP-005-2, and TOP-006-2, which remove requirements for the reliability coordinator to monitor and analyze system operating limits other than interconnection reliability operating limits.