← Energy + Nuclear Federal Register rules

Transmission Planning Reliability Standards

electric-grid · Federal Energy Regulatory Commission · Published 2012-05-07 · Effective 2012-07-06 · 77 FR 26686

Document

Document number
2012-10944
Federal Register citation
77 FR 26686
CFR reference
18 CFR 40
Type
Rule
Action
Final rule.
Category
electric-grid
Sub-agency
Federal Energy Regulatory Commission
Publication date
2012-05-07
Effective date
2012-07-06
Energy docket
Docket No. RM11-18-000

Abstract

Under section 215 of the Federal Power Act, the Federal Energy Regulatory Commission remands proposed Transmission Planning (TPL) Reliability Standard TPL-002-0b, submitted by the North American Electric Reliability Corporation (NERC), the Commission-certified Electric Reliability Organization. The proposed Reliability Standard includes a provision that allows for planned load shed in a single contingency provided that the plan is documented and alternatives are considered and vetted in an open and transparent process. The Commission finds that this provision is vague, unenforceable and not responsive to the previous Commission directives on this matter. Accordingly, the Final Rule remands NERC's proposal as unjust, unreasonable, unduly discriminatory or preferential, and not in the public interest.