# Open Access and Priority Rights on Interconnection Customer's Interconnection Facilities
> **Federal Energy Regulatory Commission** · Final rule. · Published 2015-04-01 · Effective 2015-06-30 · 80 FR 17654
## Document
- **Document number:** 2015-06953
- **Category:** electric-grid
- **Sub-agency:** Federal Energy Regulatory Commission
- **Federal Register citation:** 80 FR 17654
- **CFR reference:** 18 CFR 35
- **Publication date:** 2015-04-01
- **Effective date:** 2015-06-30
- **Energy docket:** RM14-11-000
## Abstract

In this Final Rule, the Federal Energy Regulatory Commission is amending its regulations to waive the Open Access Transmission Tariff requirements, the Open Access Same-Time Information System requirements, and the Standards of Conduct requirements, under certain conditions, for the ownership, control, or operation of Interconnection Customer's Interconnection Facilities (ICIF). This Final Rule finds that those seeking interconnection and transmission service over ICIF that are subject to the blanket waiver adopted herein may follow procedures applicable to requests for interconnection and transmission service under sections 210, 211, and 212 of the FPA, which also allows the contractual flexibility for entities to reach mutually agreeable access solutions. This Final Rule establishes a modified rebuttable presumption for a five-year safe harbor period to reduce risks to ICIF owners eligible for the blanket waiver during the critical early years of their projects. Finally, this Final Rule modifies, as described in detail below, several elements of the Notice of Proposed Rulemaking, including the entities eligible for the OATT waiver, the date on which the safe harbor begins, the rebuttable presumption that the ICIF owner should not be required to expand its facilities during the safe harbor, and the facilities covered by the Final Rule.