← Energy + Nuclear Federal Register rules

Natural Gas Pipelines; Project Cost and Annual Limits

natural-gas-pipeline · Federal Energy Regulatory Commission · Published 2016-02-22 · Effective 2016-02-22 · 81 FR 8644

Document

Document number
2016-03507
Federal Register citation
81 FR 8644
CFR reference
18 CFR 157
Type
Rule
Action
Final rule.
Category
natural-gas-pipeline
Sub-agency
Federal Energy Regulatory Commission
Publication date
2016-02-22
Effective date
2016-02-22
Energy docket
Docket No. RM81-19-000

Abstract

Pursuant to the authority delegated by 18 CFR 375.308(x)(1), the Director of the Office of Energy Projects (OEP) computes and publishes the project cost and annual limits for natural gas pipelines blanket construction certificates for each calendar year.

Source

Authoritative
Federal Register document
Machine
JSON-LD · Markdown