# Regulations Implementing FAST Act Section 61003-Critical Electric Infrastructure Security and Amending Critical Energy Infrastructure Information; Availability of Certain North American Electric Reliability Corporation Databases to the Commission; Correction
> **Federal Energy Regulatory Commission** · Final rule; correction. · Published 2017-01-05 · Effective 2017-01-05 · 82 FR 1183
## Document
- **Document number:** 2016-31541
- **Category:** electric-grid
- **Sub-agency:** Federal Energy Regulatory Commission
- **Federal Register citation:** 82 FR 1183
- **CFR reference:** 18 CFR 375
- **Publication date:** 2017-01-05
- **Effective date:** 2017-01-05
- **Energy docket:** Docket Nos. RM16-15-000, RM15-25-001
## Abstract

This document contains corrections to the final rule (RM16-15- 000, RM15-25-001) which published in the Federal Register on Wednesday, December 21, 2016 (81 FR 93732). The final rule amended the Commission's regulations to implement provisions of the Fixing America's Surface Transportation Act that pertain to the designation, protection and sharing of Critical Electric Infrastructure Information.

## Source
- [Federal Register document](https://www.federalregister.gov/documents/2017/01/05/2016-31541/regulations-implementing-fast-act-section-61003-critical-electric-infrastructure-security-and)
---