electric-grid · Federal Energy Regulatory Commission · Published 2017-09-27 · Effective 2017-11-27 · 82 FR 44918
Document
Document number
2017-20669
Federal Register citation
82 FR 44918
CFR reference
18 CFR 40
Type
Rule
Action
Final rule.
Category
electric-grid
Sub-agency
Federal Energy Regulatory Commission
Publication date
2017-09-27
Effective date
2017-11-27
Energy docket
Docket No. RM16-20-000
Abstract
The Federal Energy Regulatory Commission approves Reliability Standard PRC-012-2 (Remedial Action Schemes) submitted by the North American Electric Reliability Corporation. The purpose of Reliability Standard PRC-012-2 is to ensure that remedial action schemes do not introduce unintentional or unacceptable reliability risks to the bulk electric system.