← Energy + Nuclear Federal Register rules

Preliminary Permits, Qualifying Conduit Hydropower Facilities, and Commencement for Payment of Annual Charges

hydroelectric · Federal Energy Regulatory Commission · Published 2019-03-06 · Effective 2019-04-05 · 84 FR 7988

Document

Document number
2019-03742
Federal Register citation
84 FR 7988
CFR reference
18 CFR 4
Type
Rule
Action
Final rule.
Category
hydroelectric
Sub-agency
Federal Energy Regulatory Commission
Publication date
2019-03-06
Effective date
2019-04-05
Energy docket
Docket No. RM19-13-000

Abstract

The Federal Energy Regulatory Commission (Commission) issues this final rule to amend its regulations to conform to the enacted America's Water Infrastructure Act of 2018 (Water Infrastructure Act). This final rule revises regulations on preliminary permits, qualifying conduit hydropower facilities, and commencement for payment of annual charges. All revisions in this final rule are ministerial in nature.