← Energy + Nuclear Federal Register rules

Hydroelectric Licensing Regulations Under the America's Water Infrastructure Act of 2018

hydroelectric · Federal Energy Regulatory Commission · Published 2019-04-24 · Effective 2019-07-23 · 84 FR 17064

Document

Document number
2019-08239
Federal Register citation
84 FR 17064
CFR reference
18 CFR 7
Type
Rule
Action
Final rule.
Category
hydroelectric
Sub-agency
Federal Energy Regulatory Commission
Publication date
2019-04-24
Effective date
2019-07-23
Energy docket
Docket No. RM19-6-000

Abstract

In this final rule, the Federal Energy Regulatory Commission (Commission) is establishing an expedited process for issuing original licenses for qualifying facilities at existing nonpowered dams and for closed-loop pumped storage projects, pursuant to sections 3003 and 3004 of the America's Water Infrastructure Act of 2018. Under the expedited licensing process, the Commission will seek to ensure that a final decision is issued no later than two years after the Commission receives a completed license application. The final rule will be codified in a new part that will be added to the Commission's regulations.

Source

Authoritative
Federal Register document
Machine
JSON-LD · Markdown