# Qualifying Facility Rates and Requirements Implementation Issues Under the Public Utility Regulatory Policies Act of 1978
> **US Department of Energy** · Rule · Published 2020-12-30 · Effective 2021-02-16 · 85 FR 86656
## Document
- **Document number:** 2020-26106
- **Category:** other
- **Sub-agency:** US Department of Energy
- **Federal Register citation:** 85 FR 86656
- **CFR reference:** 18 CFR 292
- **Publication date:** 2020-12-30
- **Effective date:** 2021-02-16
- **Energy docket:** Docket Nos. RM19-15-001 and AD16-16-001
## Abstract

In this Order, the Federal Energy Regulatory Commission addresses arguments raised on rehearing and clarifies, in part, its final rule adopting revisions to its regulations implementing sections 201 and 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA). These changes will enable the Commission to continue to fulfill its statutory obligations under sections 201 and 210 of PURPA.

## Source
- [Federal Register document](https://www.federalregister.gov/documents/2020/12/30/2020-26106/qualifying-facility-rates-and-requirements-implementation-issues-under-the-public-utility-regulatory)
---
*AI Analytics · CC0 1.0*