# Improvements to Generator Interconnection Procedures and Agreements
> **US Department of Energy** · Final rule. · Published 2023-09-06 · Effective 2023-11-06 · 88 FR 61014
## Document
- **Document number:** 2023-16628
- **Category:** other
- **Sub-agency:** US Department of Energy
- **Federal Register citation:** 88 FR 61014
- **CFR reference:** 18 CFR 35
- **Publication date:** 2023-09-06
- **Effective date:** 2023-11-06
- **Energy docket:** Docket No. RM22-14-000
## Abstract

The Federal Energy Regulatory Commission (Commission or FERC) is adopting reforms to its pro forma Large Generator Interconnection Procedures, pro forma Small Generator Interconnection Procedures, pro forma Large Generator Interconnection Agreement, and pro forma Small Generator Interconnection Agreement to address interconnection queue backlogs, improve certainty, and prevent undue discrimination for new technologies. The reforms are intended to ensure that the generator interconnection process is just, reasonable, and not unduly discriminatory or preferential.

## Source
- [Federal Register document](https://www.federalregister.gov/documents/2023/09/06/2023-16628/improvements-to-generator-interconnection-procedures-and-agreements)
---