Regulatory Guide: Installation, Inspection, and Testing for Class 1E Power, Instrumentation, and Control Equipment at Production and Utilization Facilities
other · Nuclear Regulatory Commission · Published 2024-04-25 · 89 FR 31602
Document
Document number
2024-08720
Federal Register citation
89 FR 31602
CFR reference
10 CFR 50
Type
Rule
Action
Final guide; issuance.
Category
other
Sub-agency
Nuclear Regulatory Commission
Publication date
2024-04-25
Energy docket
NRC-2023-0216
Abstract
The U.S. Nuclear Regulatory Commission (NRC) is issuing Revision 1 to Regulatory Guide (RG) 1.30, "Installation, Inspection, and Testing for Class 1E Power, Instrumentation, and Control Equipment at Production and Utilization Facilities." This RG describes an approach that is acceptable to the NRC staff to meet the regulatory requirements for installation, inspection, and testing for Class 1E power, instrumentation, and control equipment at production and utilization facilities.