Delegation of Authority Regarding Electric Reliability Organization's Delegation Agreement and Rules or Rule Changes Filings
electric-grid · Federal Energy Regulatory Commission · Published 2025-09-30 · Effective 2025-09-30 · 90 FR 46752
Document
Document number
2025-18977
Federal Register citation
90 FR 46752
CFR reference
18 CFR 375
Type
Rule
Action
Final rule.
Category
electric-grid
Sub-agency
Federal Energy Regulatory Commission
Publication date
2025-09-30
Effective date
2025-09-30
Energy docket
Docket No. RM25-13-000
Abstract
The Commission is issuing this final rule to transfer certain delegated authority from the Director of the Commission's Office of Energy Market Regulation to the Director of the Commission's Office of Electric Reliability, with respect to uncontested Electric Reliability Organization (ERO) or Regional Entity filings pertaining to ERO delegation agreements and ERO or Regional Entity rules or rule changes.