Release of Firm Capacity on Interstate Natural Gas Pipelines
natural-gas-pipeline · Federal Energy Regulatory Commission · Published 1995-06-08 · Effective 1995-07-10 · 60 FR 30186
Document
Document number
95-14012
Federal Register citation
60 FR 30186
CFR reference
18 CFR 284
Type
Rule
Action
Final rule; order granting rehearing.
Category
natural-gas-pipeline
Sub-agency
Federal Energy Regulatory Commission
Publication date
1995-06-08
Effective date
1995-07-10
Energy docket
Docket No. RM95-5-001
Abstract
The Federal Energy Regulatory Commission is amending its capacity release regulations, which permit shippers to release capacity without having to comply with the Commission's advance posting and [[Page 30187]] bidding requirements. The current regulation permits such releases for a full calendar month. The Commission is revising the regulation to permit exempt releases for up to 31 days in order to accommodate releases crossing calendar months.