# Randy Ferguson
> **Administrative - Formal** · FY2008 · — · Final Order With Penalty
## Case
- **Activity ID:** `1000000818`
- **Case Number:** 06-2008-1876
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Randy Ferguson (complaint) (settlement)
## Summary

Violations: 1. Failure to post the Storm Water Construction General Permit certification, a copy 
of the Notice of Intent confirmation letter, and a brief description of the project including permit number.
2. Failure to install adequate control measures and stabilization practices at the construction site. 3. Failure
to perform required inspections of the construction site. 4. Failure to complete and certify inspection reports.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*