Las Carolinas Construction Corp.

Administrative - Formal · FY2008 · — · Final Order With Penalty · 1000004072

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2008-3319
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

Construction of 40 acre ceased aftet land was graded and cleared, but not stablized. Facility does did not do site inspections after construction ceased in October 2006