# SCITUATE CONCRETE PIPE
> **Administrative - Formal** · FY2008 · — · Final Order With Penalty
## Case
- **Activity ID:** `1000011256`
- **Case Number:** 01-2008-2071
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- SCITUATE CONCRETE PIPE (SB) (complaint)
## Summary

On April 30, 2008, an authorized representative of EPA, conducted a SPCC inspection at Scituate Concrete Pipe Co. Although Scituate Concrete Pipe Co. stores oil in amounts above the thresholds requiring the preparation and implementation of a SPCC plan under 40 C.F.R. Part 112, it did not have an adequate SPCC plan.  Because of the size of the facilities and other factors, EPA is utilizing the ESA enforcement tool.

---