- D. R. Horton, Inc. - Torrey (complaint) (settlement)
## Summary

7/31/2003 - Compliance Order issued.  Respondent failed to properly design, install and maintain temporary sedimentation pond #2, which is located in a tributary thence to Rocky Creek a navigable waters of the United States. [Part VI.D. & N]  Failed to install erosion and sediment controls along stream bank at sedimentation pond #2 to prevent discharge of sediment into Rocky Creek a navigable watersof the U.S. [Part VI.D.& N.]  Failed to properly install and maintain silt fencing around perimert of the construction site (failed to trench silt fencing and silt fences appeared to be filled to greater than 50% of its capacity).  Sediment was observed in the wetlands 35 feet from construction site. [Part VI.D. & N.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*