# IDAHO TRANSPORTATION DEPARTMENT AND SCARSELLA BROTHERS INC
> **Judicial** · FY2003 · — · Final Order With Penalty
## Case
- **Activity ID:** `101615`
- **Case Number:** 10-2003-0132
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Idaho Transportation Department (complaint) (settlement)
- Scarsella Brothers Inc (complaint) (settlement)
## Summary

Violations of the Clean Water Act during the construction of the Bellgrove-Mica realignment of Highway 95 near Lake Coeur d'Alene in Northern Idaho.  On August 1, 2011, the U.S. District Court, District of Idaho filed a ORDER GRANTING JOINT MOTION TO TERMINATE CONSENT DECREE.  The Consent Decree entered by the Court on June 23, 2006, is hereby TERMINATED.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*