BOSTON EDISON/PILGRIM POWER PLANT

Administrative - Formal · FY1999 · — · — · 1047

$173K
Penalty
Cost recovery
$2K
Compliance action

Case

Case Number
01-1999-0058
Type
Administrative - Formal
Lead
EPA
Outcome
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

BOSTON EDISION FAILED TO PROPERLY MANAGE ITS HAZARDOUS WASTE INCLUDING LABELING, DATING, GREATER THAN 90 DAY STORAGE OF INCOMPATIBLE WASTES, STORAGE OF HAZARDOUS WASTE IN CONTAINERS THAT WERE IN POOR CONDITION AND FAILED TO CONDUCT WASTE DETERMINATIONS, TRAINING AND INSPECTIONS.

Source

Authoritative
EPA ECHO
Machine