# CENTRAL MAINE POWER (OCONNOR SUPERFUND SITE)
> **Judicial** · FY2003 · — · Final Order With Unspecified Cost Recovery
## Case
- **Activity ID:** `105065`
- **Case Number:** 01-2003-0147
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Unspecified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- CENTRAL MAINE POWER (complaint) (settlement)
## Summary

AN AMENDMENT TO THE CONSENT DECREE WAS COMPLETED TO ADDRESS NEW CONDITIONS NOT SEEN ON THE SITE AT THE TIME OF THE 1990 CONSENT DECREE.

---