Oberto E. Marini Irizarry, P.E., Construction Partner, Estancias de Monte Rio, S.E.

Administrative - Formal · FY2003 · — · Unilateral Administrative Order Without Adjudication · 105138

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2003-3503
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

Illegal discharge of earthen fill into stream and into freshwater wetlands affecting 0.16 acres. As compensatory mitigation, Respondent shall conduct creation/restoration of 2.0 acres of wetlands and stream at a cost of approximately $210,000.00.