MANCHESTER STP

Administrative - Formal · FY1999 · — · Final Order No Penalty · 1064

Penalty
Cost recovery
$52.40M
Compliance action

Case

Case Number
01-1999-0075
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

COMPLIANCE ORDER WAS ISSUED TO REQUIRE PHASE I OF THE CSO ABATEMENT PROJECTS IMPLEMENTATION WITHIN 10 YEARS. QLTCP UPDATE TO EVALUATE PHASE I PROJECTS EFFECTIVENESS, AND TO DETERMINE PHASE II PROJECTS SUPPLEMENTAL ENVIRONMENTAL PROJECTS COSTING $5.6 MILLION AND REQUIRED TO BE COMPLETED WITHIN 5 YEARS.