# PIONEER CONCRETE, INC
> **Administrative - Formal** · FY2004 · — · Final Order No Penalty
## Case
- **Activity ID:** `108096`
- **Case Number:** 03-2004-0046
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- PIONEER CONCRETE, INC (SB) (complaint) (settlement)
## Summary

RESPONDENT'S FAILURE TO IMPLEMENT TO STORM WATER PLAN AS REQUIRED BY THE GENERAL PERMIT MAY HAVE CONTRIBUTED TO THE UNAUTHORIZED DISCHARGE OF POLLUTANTS TO THE CHRISTINA RIVER.

---