# BURGESS BROTHERS INC ET AL
> **Judicial** · FY1999 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `1096`
- **Case Number:** 01-1999-0107
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** $374K
- **Compliance action $:** $3.60M
- **Multimedia (multi-env):** N
## Defendants
- BURGESS BROTHERS INC (complaint) (settlement)
- CLUDE BURGESS JR (complaint) (settlement)
- CLYDE HOWE (complaint) (settlement)
- EVEREADY BATTERY CO (complaint) (settlement)
- UNION CARBIDE (complaint) (settlement)
## Summary

CD Amendment:  Amended SOW entered on 10/18/2012.

Original Case Summary: THIS CASE IS A CONSENT DECREE UNDER SECTIONS 106 AND 107  OF CERCLA AND SECTION 7003 OF RCRA. THE CD REQUIRES THE      SETTLING DEFENDANTS TO PERFORM THE ENTIRE REMEDY FOR THE SITE. AS SET FORTH IN THE RECORD OF DECISION(II), PAY 100%   OF FUTURE OVERSIGHT COSTS; (III) PAY $374,144 TO SETTLE OUTSTANDING PAST COSTS; AND (IV) PAY $100,000 FOR SETTLEMENT OF NATURAL RESOURCE DAMAGES. THIS IS A REMEDIAL ACTION/REMEDIAL DESIGN SETTLEMENT AT AN NPL SITE.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*