← EPA enforcement cases

GREEN MOUNTAIN POWER CORP (PINE ST CANAL)

Judicial · FY1999 · — · Final Order With Specified Cost Recovery · 1103

Penalty
$5.25M
Cost recovery
$6.89M
Compliance action

Case

Case Number
01-1999-0114
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
DOJ Docket
90-113-409A
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

THE PRPS HAVE AGREED TO PERFORM THE REMEDIAL DESIGN/ REMEDIAL ACTION FOR THE PINE STREET SITE; PAY $5.25 MILLION PLUS. INTEREST ON PAST RESPONSE COSTS; PAY 100% OF EPA'S OVERSIGHT OF THE RD/RA; AND PERFORM NATURAL RESERVE DAMAGE COMPENSATION PROJECTS.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown