Defendants (1)

Summary

IN MARCH 2001, RESPONDENT AND/OR HIS EMPLOYEES AND/OR CONTRACTORS, COMMENCED CONSTRUCTION OF TRACE CREEK DAM. THIS CONSTRUCTION CAUSED DISCHARGE OF DREDGED OR FILL MATERIAL INTO TRACE CREEK, AND INTO WETLANDS ADJACENT TO AND ASSOCIATED WITH TRACE CREEK, WATERS OF THE UNITED STATES.