IACAVAZZI, COSMO (AIR PRODUCTS)

Judicial · FY1987 · — · Final Order With Specified Cost Recovery · 11352

Penalty
$5.79M
Cost recovery
Compliance action

Case

Case Number
03-1987-0288
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
DOJ Docket
90-11-3-266
Multimedia
N
Self-disclosure
N

Defendants (50)

Summary

THIS IS A CERCLA 107 CASE TO BE FILED BY DOJ AGAINST APPROXIMATELY 30 GENERATORS, TRANSPORTERS, AND OWNER- DEFENDANTS. THE REMDIAL ACTION IS TO BE COMPLETED FOR THE SUMMER OF 1989 AT THE DOCHAUANN REFUSE SITE AND IS EXPECTED TO COST APPROXIMATELY 25 MILLION ($25,000,000) DOLLARS. THERE ARE THREE PITS AT THE SITE FILLED WITH MUNCIPAL AND INDUSTRIAL WASTES AND ONE ALSO CONTAINS APPROXIMATELY 8,000 DRUMS OF HAZARDOUS WASTES MATERIALS.