4/1/04 - ADMINISTRATIVE ORDER ISSUED. VIOLATIONS: NEITHER EPA NOR FDEP HAVE A RECORD OF RECEIPT OF A NOTICE OF INTENT IN THEIR RESPECTIVE DATABASES USED TO TRACK NOI SUBMISSIONS. A NOI IS REQUIRED BY PART III.A.1 OF THE PERMIT AND MUST BE SUBMITTED AT LEAST TWO DAYS PRIOR TO COMMENCEMENT OF CONSTRUCTION. NO POSTING OF THE NOI OR A COPY OF THE PERMIT COVERAGE NOTICE WAS FOUND AT THE SITE AS REQUIRED BY PART III.A.4 OF THE PERMIT.
ORDER REQUIRES:
A. WITHIN 7 CALENDAR DAYS, BEAZER HOMES SHALL SUBMIT AN INDIVIDUAL PERMIT APPLICATION OR A NOI FOR COVERAGE OF THE FACILITY UNDER THE FDEP PERMIT. A COPY OF THE PERMIT APPLICATION OR NOI SHALL BE PROVIDED TO EPA AND FDEP. IF BEAZER HOMES MAINTAINS A COPY OF A PERMIT COVERAGE NOTICE, THEN BEAZER HOMES SHALL SUBMIT A COPY OF SUCH NOTICE TO BOTH EPA AND FDEP. SHOULD CONSTRUCTION AT THE WINDSOR LANDING SITE BE COMPLETE, THEN BEAZER HOMES SHALL COMPLETE A NOT AND PROVIDE A COPY TO BOTH EPA AND FDEP.
B. WITHIN 30 DAYS, BEAZER HOMES SHALL DEVELOP AND IMPLEMENT A SWPP. WITHIN 40 DAYS, BEAZER HOMES SHALL PROVIDE WRITTEN CERTIFICATION THAT IT HAS DEVELOPED AND IMPLEMENTED ITS SWPPP, AND IT KEEPS A COPY OF THE SWPPP ON SITE OR AN ACCESSIBLE LOCATION, AND THAT ITS BMP PLAN COMPLIES WITH PART V OF THE PERMIT.
C. WITHIN 7 CALENDAR DAYS, BEAZER SHALL IMPLEMENT MAINTENANCE PROVISIONS AT ITS FACILITY TO ENSURE THAT TIMELY MAINTENANCE OF VEGETATION, EROSION AND SEDIMENT CONTROLS, STORMWATER MANAGEMENT PRACTICES, AND OTHER PROTECT