4/1/04 - COMPLIANCE ORDER ISSUED.
VIOLATIONS: RYLAND HOMES STATED IN A FACSIMILE ON AUGUST 12, 2003, TO SAIC THAT THE NOTICE OF INTENT (NOI) WAS SUBMITTED ON FEBRUARY 11, 2002. NEITHER EPA OR THE FLORIDA DEPT OF ENVIRONMENTAL PROTECTION HAVE A RECORD OF RECEIPT OF THE NOI IN THEIR RESPECTIVE DATABASES USED TO TRACK NOI INFORMATION. A NOI IS REQUIRED BY PART II.A.2 OF THE NPDES PERMIT AND MUST BE SUBMITTED AT LEAST TWO DAYS PRIOR TO COMMENCEMENT OF CONSTRUCTION. NO POSTING OF THE NOI OR A DESCRIPTION OF THE WORK TO BE COMPLETED WAS FOUD AT THE SITE AS REQUIRED BY PART II.C.2 OF THE NPDES PERMIT.
ORDER REQUIRES:
WITHIN 7 CALENDAR DAYS, RYALND HOMES SHALL SUBMIT AN INDIVIDUAL PERMIT APPLICATION OR A NOI FOR COVERAGE OF THE FACILITY UNDER THE FDEP PERMIT. A COPY OF THE PERMIT APPLICATION OR NOI SHALL BE PROVIDED TO EPA AND FDEP. IF RYLAND HOMES MAINTAINS A COPY OF A PERMIT COVERAGE NOTICE ISSUED BY EPA FOR WESTFIELD LAKES, THEN RYLAND HOMES SHALL SUBMIT A COPY OF SUCH NOTICE TO BOTH EPA AND FDEP. IF CONSTRUCTION HAS BEEN COMPLETED, THEN RYLAND HOMES SHALL COMPLETE A NOT AND SHALL PROVIDED A COPY TO BOTH EPA AND FDEP WITHIN 7 DAYS.
WITHIN 30 DAYS, RYLAND HOMES SHALL DEVELOP AND IMPLEMENT A SWPPP. WITHIN 40 CALENDAR DAYS, RYLAND HOMES SHALL PROVIDE WRITTEN CERTIFICATION THAT IT HAS DEVELOPED AND IMPLEMENTED ITS SWPPP, THAT IT KEEPS A COPY OF THE SWPPP ON SITE OR AN ACCESSIBLE LOCATION, AND THAT ITS BMP PLAN COMPLIES WITH PART V OF THE FDEP PERMIT.
WITHIN 7