# PAC Construction Services Corp. (SB)
> **Administrative - Formal** · FY2004 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `122621`
- **Case Number:** 02-2004-1029
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- PAC Construction Services Corp. (SB) (complaint) (settlement)
## Summary

Belated Notifiicatinon,  no financial penalty, but must provide a log of all jobs performed during the 90-day interval following receipt of the AO.  This includes even those jobs that are too small to require a regular notification.  The contractor must still provide all regular notifications where the scope of the job warrants it.  The 90-day reports does not exempt the contractor from providing notifications.

---