# Oceaneering International-0915
> **Administrative - Formal** · FY2004 · — · Final Order With Penalty
## Case
- **Activity ID:** `122958`
- **Case Number:** 06-2004-0915
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Oceaneering International (complaint) (settlement)
## Summary

On May 8, 2003 EPA inspectors observed and documented violations at the facility.  The violations were, failing to meet exemption requirements of 30 TAC  335.69 [40 C.F.R. 262.34].  The facility was issued an Expedited Consent Agreement and Final Order on July 8, 2004 with a penalty amount of $2,000. The penalty have been paid and the violations cleared.

---