Brasfield & Gorrie, LLC (TXU010406)

Administrative - Formal · FY2004 · — · Unilateral Administrative Order Without Adjudication · 123942

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2004-2302
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

BRASFIELD & GORRIE, LLC (TXU010406): Respondent was general contractor for the Texarkana Pavilion, in Texarkana, TX. Although they had developed a Storm Water Pollution Prevention Plan (SWPPP) and had permit coverage under the federal Construction General Permit, they had failed to reapply to the Texas Commission on Environmental Quality (TCEQ) once the TCEQ reissued that permit on March 5, 2003. The inspector noted the SWPPP deficient. Because the Respondent met the criteria, an Expedited Settlement Offer (ESO) was drafted and routed for signature.