7/29/04 - COMPLIANCE ORDER ISSUED.  

VIOLATIONS:

FAILURE TO TAKE CORRECTIVE ACTION IMMEDIATELY TO CONTROL THE DISCHARGE OF SEDIMENTS;

FAILURE TO MAINTAIN A RECORD OF THE EROSION AND SEDIMENT CONTROL SITE INSPECTIONS PRIOR TO APRIL 26, 2004;

FAILURE TO ADEQUATELY INSTALL AND/OR MAINTAIN TEMPORARY OR PERMANENT MEASURES THROUGHOUT THE SITE TO CONTROL  AND RETAIN SEDIMENT, INCLUDING SILT FENCING; CONSTRUCTION ENTRANCES AND EXITS; STORM INLET PROTECTION; DIVERSION DITCHES; OUTLET AND OUTFALL PROTECTION; LACK OF ADEQUATE GROUNDCOVER AROUND THE SLOPES AND SEDIMENTATION BASINS; INSTALLING AND CONNECTING STORM DRAIN INFRASTRUCTURE INTO PERMANENT OUTFALLS PRIOR TO SITE STABILIZATION INSTEAD OF CONNECTING TO TEMPORARY SEDIMENTATION BASINS; AND INADEQUATE OR LACK OF CONSTRUCTION OF SEDIMENTATION BASINS AND SILT TRAPS

---