CENTREDALE MANOR RESTORATION PROJECT SUPERFUND SITE

Administrative - Formal · FY2000 · — · — · 1247

Penalty
Cost recovery
$200K
Compliance action

Case

Case Number
01-2000-0050
Type
Administrative - Formal
Lead
EPA
Outcome
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

   THIS UAO REQUIRES THE 5 SITE PRPS TO COMPLETE THE TIME    CRITICAL REMOVAL ACTIVITIES REQUIRED AT THE SITE (EPA        STOPPED ITS TIME CRITICAL REMOVAL ACTIVITIES FOR THE WINTER  AND ATTEMPTED TO NEGOTIATE AN AOC). COMPLETION OF SECOND     CAP AND INSTALLATION OF CERTAIN FLOOD CONTROL.            Â