# RYLAND HOMES (PROVIDENCE GROVE)
> **Administrative - Formal** · FY2004 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `125061`
- **Case Number:** 04-2004-4801
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- RYLAND HOMES (settlement)
## Summary

7/30/04 - COMPLIANCE ORDER ISSUED.  

VIOLATIONS:

FAILURE TO TAKE CORRECTIVE ACTION IMMEDIATELY TO CONTROL THE DISCHARGE OF SEDIMENTS;

FAILURE TO MAINTAIN A RECORD OF THE EROSION AND SEDIMENT CONTROL FACILITY INSPECTION;

FAILURE TO ADEQUATELY INSTALL AND/OR MAINTAIN TEMPORARY OR PERMANENT MEASURES THROUGHOUT THE SITE TO CONTROL AND RETAIN SEDIMENT, INCLUDING SILT FENCING; CONSTRUCTION ENTRANCES AND EXITS; STORM INLET PROTECTION; OUTLET AND OUTFALL PROTECTION; LFACK OF ADEQUATE GROUNDCOVER AROUND THE SLOPES AND SEDIMENTATION BASINS; INSTALLING AND CONNECTING SOTRM DRAIN INFRASTRUCTURE INTO PERMANENT OUTFALLS PRIOR TO SITE STABILIZATION INSTEAD OF CONNECTING TO TEMPORARY SEDIMENTATION BASINS; INADEQUATE SLOPE GRADES AT STREAM CROSSINGS; AND INADEQUATE CONSTRUCTION OF SEDIMENTATION BASIN

---