NIPSCO

Judicial · FY2004 · — · Final Order With Penalty · 131953

Penalty
Cost recovery
Compliance action

Case

Case Number
05-2004-4533
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

CAPITAL PROJECTS WERE CONDUCTED AT THE MICHIGAN CITY, R.M. SCHAHFER AND BAILLY GENERATING STATIONS THAT THE U.S. EPA CONSIDERS MAJOR MODIFICATIONS UNDER THE APPLICABLE PSD REGULATIONS. NIPSCO SHOULD HAVE SUBMITTED A REQUEST FOR A PSD APPLICABILITY DETERMINATION AND ACQUIRED PSD PERMITS FOR EACH OF THE BELOW PROJECTS BECAUSE EACH OF THE PROJECTS WAS A MAJOR MODIFICATION. NIPSCOS FAILURE TO SUBMIT AN APPLICATION FOR A PSD APPLICABILITY DETERMINATION AND ACQUIRE A PSD PERMIT FOR EACH OF THE PROJECTS IS A VIOLATION OF THE APPLICABLE PSD REGULATIONS.