City of Detroit, Department of Public Lighting

Administrative - Formal · FY2004 · — · Final Order With Penalty · 132963

Penalty
Cost recovery
Compliance action

Case

Case Number
05-2004-3712
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

Mistersky will be required to achieve, demonstrate and maintain compliance with the Acid Rain Program for the affected units including completion of initial certifications, performing of RATAs and a certification that all units are in compliance with the Acid Rain Program within one year of the effective date of the Administrative Order. A CAFO will resolve past violations that have already been corrected and to collect a penalty for all Acid Rain Program and NSPS violations.