# TRAM LLC (HARWINTON HEIGHTS)
> **Administrative - Formal** · FY2004 · — · Final Order No Penalty
## Case
- **Activity ID:** `133147`
- **Case Number:** 01-2004-2107
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- TRAM LLC (complaint) (settlement)
## Summary

THE ORDER REQUIRES SUBMISSION OF A REVISED SWPPP, AND AN EVALUATION OF THE ALTERNATIVE STORMWATER MEASURES THAT ARE NECESSARY TO ENSURE THAT THE CONSTRUCTION SITE COMPLIES WITHTHE POST-CONSTRUCTION REQUIREMENTS OF THE CTDEP's CONSTRUCTION GENERAL STORMWATER PERMIT.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*