# DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY
> **Administrative - Formal** · FY2005 · — · Final Order No Penalty
## Case
- **Activity ID:** `135671`
- **Case Number:** 03-2005-0025
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- DISTRICT OF COLUMBIA WATER AND SEWER SYSTEM AUTHOR (complaint) (settlement)
## Summary

FAILURE TO REPLACE AT LEAS 7% OF LEAD SERVIC ELINES FOLLOWING EXCEEDANCE OF LEAD ACTION LEVEL.

PHYSICAL REPLACE OF LEAD SERVICE LINES.  CUSTOMER NOTIFICATION OF SAMPLING ERRORS.

---