Summary of Findings:
* Plan not certified by a profession engineer.
* Plan has inadequatae or no information and procedures for reporting a discharge.
* Plan has inadequate or no description and procedures to use when a discharge may occur.
* Plan has inadequate or no discussion of personnel and spill prevention procedures.
* Plan has inadequate or no discussion of facility security.
* Plan has inadequate or no discussion of facility tank car and tank truck loading/unloading rack.
* Plan has inadequate or no discussion of bulk storage tanks.
* Plan has inadequate or no discussion of facility transfer operations, pumping, and facility process.