Summary of Findings:

* Plan not certified by a professional engineer.

* No management aporoval of plan.

* Written procedures and inspection records are not kept with the plan.

* Oil drainage collection equipment is not utilized to prevent and control small oil discharges around equipment and/or oil is not removed from collection equipment to prevent overflows.

* Sump system, if used, is not adequataely sized and/or no spare pump available.

* Atmospheric storage/surge containers are not equipped with high level sensing devices that activate an alarm or control flow.

---