# TX-Morrow  Construction, Inc.
> **Administrative - Formal** · FY2005 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `136258`
- **Case Number:** 06-2005-1770
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- TX-Morrow Construction, Inc. (complaint) (settlement)
## Summary

August 5, 2004, EPA inspection found the Carington Place facility in violation of permit requirements under the NPDES federal storm water regulatory permit program.  December 2004, EPA addressed the violations at the facility with the issuance of an Expedited Settlement Offer and Administrative Order for compliance to the owner/operator TX-Morrow Construction, Inc.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*