← EPA enforcement cases

THE LINKS OF SOUTHLAND PHASE 11A AND 11B

Administrative - Formal · FY2005 · — · Unilateral Administrative Order Without Adjudication · 137011

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2005-4753
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

12/10/04 - COMPLIANCE ORDER ISSUED. FAILURE TO OBTAIN PERMIT COVERAGE AS REQUIRED BY THE GEORGIA WATER QUALITY ACT AND THE FEDERAL CWA. CSWEI ALSO REVEALED THE FOLLOWING DISCREPANCIES AT THE FACILTY: SEDIMENTS WERE OBSERVED DISCHARGING OFF-SITE AND INTO A NEARBY CREEK AS A RESULT OF BLOWN-OUT SILT FENCES. INSPECTORS ALSO OBSERVED UNSTABILIZED SLOPES AND CURB INLETS THAT WERE IMPROPERLY MAINTAINED.

Source

Authoritative
EPA ECHO
Machine