11/04/04 - ADMINISTRATIVE ORDER ISSUED. ORDER REQUIRES:
RESPONDENTS SHALL IMMEDIATELY CEASE PARTICIPATING IN, CAUSING, OR ALLOWING ANY ADDITIONAL DISCHARGED OF ANY DREDGED OR FILL MATERIAL , INTO WATERS OF THE U.S. IN THE EVENT THAT RESPONDENTS' COMPLIANCE WITH ANY STATE REQUIREMENT CONFLICTS WITH THE TERMS OF THIS ORDER, RESPONDENTS ARE DIRECTED TO CONTACT THE EPA REPRESENTATIVES IDENTIFIED IN THE COVER LETTER TRANSMITTING THIS ORDER.
WITHIN 48 HOURS OF RECEIPT, RESPONDENTS SHALL INFORM EPA WHETHER RESPONDENTS INTEND TO COMPLY WITH THIS ORDER.
WITHIN 30 DAYS, RESPONDENTS SHALL PROVIDE A DELINEATION FOR EPA APPROVAL OF ALL CURRENT AND FORMER (IMPACTED) WATERS OF THE U.S. AT THE DISCHARGE AREA.
WITHIN 30 DAYS, RESPONDENT SHALL PROVIDE A PLAN TO ASSESS THE SEDIMENTATION IMPACTS DOWN STREAM OF THE DISCHARGE AREA